| Concrete work area | Quantity | Rate | Amount |
| 01 · Front driveway80 ft by 10 ft · thickened edge | 800 sq ft | $10.50 | $8,400.00 |
| 02 · Sidewalk behind house120 ft by 8 ft · placement without removal | 960 sq ft | $10.50 | $10,080.00 |
| 03 · Back driveway42 ft by 12 ft | 504 sq ft | $10.50 | $5,292.00 |
| 04 · Gazebo pad25 ft by 31 ft | 775 sq ft | $10.50 | $8,137.50 |
| Unallocated project allowanceIncluded to reconcile requested total; no footprint assigned | 84 sq ft | $10.50 | $882.00 |
| Site-material haul-offLoading and disposal of ordinary excavated soil and project spoils; excludes existing-concrete demolition | 1 lump sum | $3,000.00 | $3,000.00 |
Included in project price
- 50 cubic yards of 3,000 PSI ready-mix concrete, including pump-line and placement-loss allowance
- Concrete pump placement for the planned pours
- Completed site survey and project layout work
- Layout, forming, staking, and standard edge forms
- Subgrade preparation and ordinary compaction
- Concrete placement, screeding, broom finish, and edging
- Control joints, standard curing, form stripping, and cleanup
- Thickened edge at front driveway as marked on plan
Estimated project totalConcrete labor and material are included at the stated unit rate; ordinary site-material haul-off is added as a lump sum. Final billing is subject to field measurement, access, site conditions, and approved scope.
$35,791.50
Required to begin work
25% mobilization deposit
Due before scheduling and commencement. The deposit secures ready-mix scheduling, tractor and compact-equipment mobilization, initial forming materials, and ordinary jobsite consumables and incidentals. It is applied to the project total.
$8,947.88Balance after deposit · $26,843.62
Excluded / by change order
- Rebar or welded-wire reinforcement — not included or planned
- Existing-concrete demolition at the rear sidewalk
- Permits and municipal fees
- Special-access or after-hours placement surcharges
- Unsuitable soil, over-excavation, imported base, or drainage correction
- Cold-weather protection or extraordinary weather measures